TWO THIRD OF TAP'S GREECE AND ALBANIA ROUTES CLEARED
Share :
Download PDF :

10.08.2017


AZERTAC 09.08.2017

More than 500 kilometers out of 765 kilometers of the Trans Adriatic Pipeline’s (TAP) route has been cleared in Greece and Albania, which is 2/3 of the pipeline’s length in those two countries, TAP AG consortium said.

TAP is a part of the Southern Gas Corridor which is one of the priority energy projects for the EU.

TAP project envisages transportation of gas from the Stage 2 of development of Azerbaijan's Shah Deniz gas and condensate field to the EU countries.

The pipeline will be connected to the Trans-Anatolian Pipeline (TANAP) on the Turkish-Greek border, run through Greece, Albania and the Adriatic Sea, before coming ashore in Italy's south.

TAP’s shareholders are: BP (20 percent), State Oil Company of Azerbaijan (20 percent), Snam (20 percent), Fluxys (19 percent), Enagas (16 percent) and Axpo (5 percent).